The South African National Roads Agency Limited (Sanral) says it is dealing with a “significant backlog in procurement”. There are a number of reasons for this, including a process between the agency and the National Treasury to seek clarification on the 30% subcontracting clause, which took 18 months to complete, as well as the interpretation of the term ‘local’, which led to the stalling of 64 Sanral projects, caused by community disruptions, says the agency.